ITAC Assessment: MZ0062
ITAC logo
ITAC Assessment: MZ0062
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Steel couplings for hydraulic hoses
NAICS 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 100
Plant Area 80,000
ft2
Annual Production 60,000,000
pieces
Production Hrs. Annual 8,000
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $462,192 7,709,300
kWh
Electricity Demand $127,096 15,887
kW-mo/yr
Natural Gas $219,588 31,823
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $233,221 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $120,057

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4221: Install compressor air intakes in coolest locations $7,242 $1,160 $7,242
120,706
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $31,772 $49,280 $25,216
420,272
kWh
$6,556
-
kW-mo/yr
-
03 2.7135: Install occupancy sensors $1,292 $1,840 $1,292
21,535
kWh
- -
04 2.7144: Install spectral reflectors / delamp $1,360 $100 $1,133
18,880
kWh
$227
-
kW-mo/yr
-
05 2.7492: Use proper thickness of insulation on building envelope $866 $1,498 - - $866
-
MMBtu
06 2.3412: Use waste heat to produce steam to drive a steam turbine-generator $89,844 $250,000 $74,868
1,247,803
kWh
$14,976
-
kW-mo/yr
-
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $26,441 $1,300 $26,441
440,690
kWh
- -
08 2.4239: Eliminate or reduce compressed air usage $8,105 $15,000 $6,723
112,055
kWh
$1,382
-
kW-mo/yr
-
09 2.4239: Eliminate or reduce compressed air usage $4,053 $9,000 $3,362
56,028
kWh
$691
-
kW-mo/yr
-
10 2.2414: Use waste heat from hot flue gases to preheat $19,502 $30,000 - - $19,502
-
MMBtu
11 2.2414: Use waste heat from hot flue gases to preheat $17,836 $10,000 - - $17,836
-
MMBtu
12 2.7492: Use proper thickness of insulation on building envelope $62 $60 - - $62
-
MMBtu
13 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $91 $300 $91
1,512
kWh
- -
14 2.1321: Replace fossil fuel equipment with electrical equipment $11,657 $150,000 $(-18,947.3)
(-315,789)
kWh
$(-3,792.0)
-
kW-mo/yr
$34,397
-
MMBtu
15 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,598 $1,500 $1,598
26,632
kWh
- -
16 2.4224: Upgrade controls on compressors $11,500 $18,000 $11,500
230,000
kWh
- -
TOTAL RECOMMENDED $233,221 $539,038 $140,519
2,380,324
kWh
$20,040
-
kW-mo/yr
$72,663
-
MMBtu
TOTAL IMPLEMENTED $120,057 $254,140 $62,761
1,084,354
kWh
$5,064
-
kW-mo/yr
$52,233
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs