Assessment Year | 2011 |
---|---|
Principal Product | Flavoring Extracts and Syrups |
NAICS | 311941: Mayonnaise, Dressing, and Other Prepared Sauce Manufacturing |
SIC | 2035: Pickled Fruits and Vegetables, Vegetable Sauces and Seasonings, and Salad Dressings |
Sales Range | $1 M to 5M |
# of Employees | 400 |
Plant Area |
330,000
ft2
|
Annual Production | 1,000
units
|
Production Hrs. Annual | 7,344
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,408,416 | 17,013,439 |
kWh
|
$0.083 |
Electricity Demand | $558,750 | 33,411 |
kW-mo/yr
|
$16.72 |
Electricity Fees | $11,691 | - |
|
- |
Natural Gas | $427,597 | 77,756 |
MMBtu
|
$5.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $413,550 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $76,479 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,198 | $2,100 |
$11,904
143,770
kWh
|
$3,294
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,180 | $2,000 |
$3,180
38,400
kWh
|
- | - | - | |
03 | 2.7135: Install occupancy sensors | $7,888 | $6,050 |
$7,888
95,265
kWh
|
- | - | - | |
04 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $1,787 | $1,535 | - | - |
$1,787
-
MMBtu
|
- | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $26,197 | $22,700 | - | - |
$26,197
-
MMBtu
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $35,598 | $52,274 |
$26,670
322,461
kWh
|
$8,928
-
kW-mo/yr
|
- | - | |
07 | 2.2121: Increase amount of condensate returned | $12,828 | $20,000 | - | - |
$12,828
-
MMBtu
|
- | |
08 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $283,465 | $607,200 |
$292,306
3,530,261
kWh
|
$101,524
-
kW-mo/yr
|
$(-66,236.6)
-
MMBtu
|
$(-44,128.0) | |
09 | 2.7145: Install skylights | $6,479 | $14,200 |
$4,874
58,862
kWh
|
$1,605
-
kW-mo/yr
|
- | - | |
10 | 2.4321: Upgrade obsolete equipment | $20,930 | $61,200 |
$20,930
252,775
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $413,550 | $789,259 |
$367,752
4,441,794
kWh
|
$115,351
-
kW-mo/yr
|
$(-25,424.6)
-
MMBtu
|
$(-44,128.0) | ||
TOTAL IMPLEMENTED | $76,479 | $83,959 |
$49,642
599,896
kWh
|
$12,222
-
kW-mo/yr
|
$14,615
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs