ITAC Assessment: MZ0060
ITAC logo
ITAC Assessment: MZ0060
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product treated and purified water
NAICS 311999: All Other Miscellaneous Food Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 25
Plant Area 190,000
ft2
Annual Production 5,000,000
ton
Production Hrs. Annual 8,760
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $423,493 4,755,185
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $149,701 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $32,699

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7135: Install occupancy sensors $32,699 $5,400 $32,699
367,000
kWh
-
02 2.4133: Use most efficient type of electric motors $6,269 $18,857 $4,573
42,088
kWh
$1,696
-
kW-mo/yr
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $329 - $329
3,620
kWh
-
04 2.4131: Size electric motors for peak operating efficiency $699 $8,922 $591
6,650
kWh
$108
-
kW-mo/yr
05 2.4112: Install soft-start to eliminate nuisance trips $103,362 $10,000 - $103,362
-
kW-mo/yr
06 2.4151: Develop a repair/replace policy $6,343 $12,500 $3,967
58,033
kWh
$2,376
-
kW-mo/yr
TOTAL RECOMMENDED $149,701 $55,679 $42,159
477,391
kWh
$107,542
-
kW-mo/yr
TOTAL IMPLEMENTED $32,699 $5,400 $32,699
367,000
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs