| Assessment Year | 2010 |
|---|---|
| Principal Product | aoto inerior products |
| NAICS | 326121: Unlaminated Plastics Profile Shape Manufacturing |
| SIC | 3083: Laminated Plastics Plate, Sheet, and Profile Shapes |
| Sales Range | $1 M to 5M |
| # of Employees | 32 |
| Plant Area |
140,000
ft2
|
| Annual Production | 24,000
pieces
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $186,700 | 1,629,000 |
kWh
|
$0.11 |
| Electricity Demand | $224,193 | 11,520 |
kW-mo/yr
|
$19.46 |
| Natural Gas | $97,279 | 8,943 |
MMBtu
|
$10.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $30,756 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $21,098 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,916 | $1,100 |
$2,470
22,457
kWh
|
$2,446
-
kW-mo/yr
|
|
| 02 | 2.7135: Install occupancy sensors | $770 | $700 |
$770
6,989
kWh
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $4,900 | $1,160 |
$2,500
22,661
kWh
|
$2,400
-
kW-mo/yr
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,282 | $16,460 |
$5,755
52,320
kWh
|
$5,527
-
kW-mo/yr
|
|
| 05 | 2.4131: Size electric motors for peak operating efficiency | $8,888 | - |
$4,533
41,216
kWh
|
$4,355
-
kW-mo/yr
|
|
| 06 | 2.4226: Use / purchase optimum sized compressor | - | - | - | - | |
| 07 | 2.7492: Use proper thickness of insulation on building envelope | - | - | - | - | |
| TOTAL RECOMMENDED | $30,756 | $19,420 |
$16,028
145,643
kWh
|
$14,728
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $21,098 | $18,720 |
$10,725
97,438
kWh
|
$10,373
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs