| Assessment Year | 2010 |
|---|---|
| Principal Product | magazines, directories, newsletters |
| NAICS | 323111: Commercial Printing (except Screen and Books) |
| SIC | 2752: Commercial Printing, Lithographic |
| Sales Range | $10 M to 50M |
| # of Employees | 62 |
| Plant Area |
49,800
ft2
|
| Annual Production | 1,200
ton
|
| Production Hrs. Annual | 5,460
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $130,220 | 1,871,522 |
kWh
|
$0.070 |
| Electricity Demand | $14,036 | 6,380 |
kW-mo/yr
|
$2.20 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $52,165 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $43,605 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $2,053 | $1,160 |
$1,913
28,984
kWh
|
$140
-
kW-mo/yr
|
|
| 02 | 2.6218: Turn off equipment when not in use | $2,616 | - |
$2,616
41,527
kWh
|
- | |
| 03 | 2.7229: Air condition only space necessary | $24,897 | $5,000 |
$23,040
384,056
kWh
|
$1,857
-
kW-mo/yr
|
|
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $585 | $6,000 |
$107
5,621
kWh
|
$478
-
kW-mo/yr
|
|
| 05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $916 | $1,000 | - |
$916
-
kW-mo/yr
|
|
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,280 | - |
$5,280
80,015
kWh
|
- | |
| 07 | 2.7135: Install occupancy sensors | $311 | $1,250 |
$311
4,713
kWh
|
- | |
| 08 | 2.6218: Turn off equipment when not in use | $15,507 | - |
$15,507
258,460
kWh
|
- | |
| TOTAL RECOMMENDED | $52,165 | $14,410 |
$48,774
803,376
kWh
|
$3,391
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $43,605 | $11,000 |
$41,270
689,664
kWh
|
$2,335
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs