ITAC Assessment: MZ0050
ITAC logo
ITAC Assessment: MZ0050
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product magazines, directories, newsletters
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 62
Plant Area 49,800
ft2
Annual Production 1,200
ton
Production Hrs. Annual 5,460
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $130,220 1,871,522
kWh
Electricity Demand $14,036 6,380
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $52,165 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $43,605

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4221: Install compressor air intakes in coolest locations $2,053 $1,160 $1,913
28,984
kWh
$140
-
kW-mo/yr
02 2.6218: Turn off equipment when not in use $2,616 - $2,616
41,527
kWh
-
03 2.7229: Air condition only space necessary $24,897 $5,000 $23,040
384,056
kWh
$1,857
-
kW-mo/yr
04 2.7232: Replace existing hvac unit with high efficiency model $585 $6,000 $107
5,621
kWh
$478
-
kW-mo/yr
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $916 $1,000 - $916
-
kW-mo/yr
06 2.4231: Reduce the pressure of compressed air to the minimum required $5,280 - $5,280
80,015
kWh
-
07 2.7135: Install occupancy sensors $311 $1,250 $311
4,713
kWh
-
08 2.6218: Turn off equipment when not in use $15,507 - $15,507
258,460
kWh
-
TOTAL RECOMMENDED $52,165 $14,410 $48,774
803,376
kWh
$3,391
-
kW-mo/yr
TOTAL IMPLEMENTED $43,605 $11,000 $41,270
689,664
kWh
$2,335
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs