Assessment Year | 2009 |
---|---|
Principal Product | rubber transmition belts |
NAICS | 326220: Rubber and Plastics Hoses and Belting Manufacturing |
SIC | 3052: Rubber and Plastics Hose and Belting |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
185,000
ft2
|
Annual Production | 10,000
ton
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,099,132 | 17,291,129 |
kWh
|
$0.064 |
Electricity Demand | $536,354 | 39,036 |
kW-mo/yr
|
$13.74 |
Natural Gas | $974,244 | 104,272 |
MMBtu
|
$9.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $102,382 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $62,602 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $14,217 | $1,000 |
$14,217
184,635
kWh
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $625 | $650 |
$625
15,400
kWh
|
- | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,996 | - |
$3,996
51,660
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $25,188 | $32,000 |
$25,188
238,680
kWh
|
- | |
05 | 2.7135: Install occupancy sensors | $5,200 | $532 |
$5,200
67,222
kWh
|
- | |
06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $39,780 | $3,000 | - |
$39,780
-
kW-mo/yr
|
|
07 | 2.5196: Use small number of high output units instead of many small inefficient units | $13,376 | $20,000 |
$13,376
126,938
kWh
|
- | |
TOTAL RECOMMENDED | $102,382 | $57,182 |
$62,602
684,535
kWh
|
$39,780
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $62,602 | $54,182 |
$62,602
684,535
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs