| Assessment Year | 2008 |
|---|---|
| Principal Product | Metal cases |
| NAICS | 332322: Sheet Metal Work Manufacturing |
| SIC | 3444: Sheet Metal Work |
| Sales Range | $10 M to 50M |
| # of Employees | 122 |
| Plant Area |
85,000
ft2
|
| Annual Production | 210,000
units
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $200,019 | 3,242,700 |
kWh
|
$0.062 |
| Natural Gas | $159,790 | 19,295 |
MMBtu
|
$8.28 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,077 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $4,642 | $900 |
$4,642
58,476
kWh
|
- | |
| 02 | 2.1122: Re-size charging openings or add a movable door on equipment | $514 | $1,400 | - |
$514
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,465 | $1,400 |
$3,465
43,300
kWh
|
- | |
| 04 | 2.2515: Use optimum thickness insulation | $76 | $300 | - |
$76
-
MMBtu
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,444 | $30,600 |
$9,444
120,058
kWh
|
- | |
| 06 | 2.2447: Heat water with exhaust heat | $9,936 | $10,000 | - |
$9,936
-
MMBtu
|
|
| TOTAL RECOMMENDED | $28,077 | $44,600 |
$17,551
221,834
kWh
|
$10,526
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs