| Assessment Year | 2008 |
|---|---|
| Principal Product | clay pots |
| NAICS | 327120: Clay Building Material and Refractories Manufacturing |
| SIC | 3269: Pottery Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 39 |
| Plant Area |
70,000
ft2
|
| Annual Production | 3,000,000
units
|
| Production Hrs. Annual | 4,600
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $162,913 | 1,664,652 |
kWh
|
$0.098 |
| Natural Gas | $306,694 | 37,197 |
MMBtu
|
$8.25 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $72,245 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $67,370 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $1,253 | $900 |
$1,253
10,988
kWh
|
- | |
| 02 | 31191: | $19,648 | $640 |
$19,648
180,459
kWh
|
- | |
| 03 | 2.5115: Reposition oven walls to reduce heated space | $2,129 | $2,700 | - |
$2,129
-
MMBtu
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,405 | $1,825 |
$10,405
99,360
kWh
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,901 | $21,600 |
$5,901
56,350
kWh
|
- | |
| 06 | 2.7124: Make a practice of turning off lights when not needed | $2,173 | - |
$2,173
18,600
kWh
|
- | |
| 07 | 2.7135: Install occupancy sensors | $1,493 | $1,475 |
$1,493
14,260
kWh
|
- | |
| 08 | 22442: | $28,309 | $18,000 | - |
$28,309
-
MMBtu
|
|
| 09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $934 | - |
$934
8,857
kWh
|
- | |
| TOTAL RECOMMENDED | $72,245 | $47,140 |
$41,807
388,874
kWh
|
$30,438
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $67,370 | $42,065 |
$39,061
363,626
kWh
|
$28,309
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs