ITAC Assessment: MZ1001
ITAC logo
ITAC Assessment: MZ1001
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product city gymnasium
NAICS 713940: Fitness and Recreational Sports Centers
SIC 7991: Physical Fitness Facilities
Sales Range less than $500
k
# of Employees 12
Plant Area 9,298
ft2
Annual Production 1
pieces
Production Hrs. Annual 2,600
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,494 274,560
kWh
Electricity Demand $14,914 892
kW-mo/yr
Natural Gas $13,181 1,117
MMBtu
Waste Disposal Costs
Water Usage $972 85
Tgal
TOTAL YEARLY COSTS $60,561
RECOMMENDED SAVINGS* $24,437 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7232: Replace existing hvac unit with high efficiency model $12,758 $83,955 $7,070
61,481
kWh
$5,688
-
kW-mo/yr
-
02 2.7135: Install occupancy sensors $507 $1,000 $507
4,404
kWh
- -
03 2.6212: Turn off equipment during breaks, reduce operating time $904 $770 $904
7,862
kWh
- -
04 2.7221: Lower temperature during the winter season and vice-versa $10,268 $2,010 $6,818
59,296
kWh
- $3,450
-
MMBtu
TOTAL RECOMMENDED $24,437 $87,735 $15,299
133,043
kWh
$5,688
-
kW-mo/yr
$3,450
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs