Assessment Year | 2024 |
---|---|
Principal Product | city gymnasium |
NAICS | 713940: Fitness and Recreational Sports Centers |
SIC | 7991: Physical Fitness Facilities |
Sales Range | less than $500 k |
# of Employees | 12 |
Plant Area |
9,298
ft2
|
Annual Production | 1
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $31,494 | 274,560 |
kWh
|
$0.11 | |
Electricity Demand | $14,914 | 892 |
kW-mo/yr
|
$16.72 | |
Natural Gas | $13,181 | 1,117 |
MMBtu
|
$11.80 | |
Waste Disposal Costs | |||||
Water Usage | $972 | 85 |
Tgal
|
$11.40 | |
TOTAL YEARLY COSTS | $60,561 | ||||
RECOMMENDED SAVINGS* | $24,437 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7232: Replace existing hvac unit with high efficiency model | $12,758 | $83,955 |
$7,070
61,481
kWh
|
$5,688
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $507 | $1,000 |
$507
4,404
kWh
|
- | - | |
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $904 | $770 |
$904
7,862
kWh
|
- | - | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $10,268 | $2,010 |
$6,818
59,296
kWh
|
- |
$3,450
-
MMBtu
|
|
TOTAL RECOMMENDED | $24,437 | $87,735 |
$15,299
133,043
kWh
|
$5,688
-
kW-mo/yr
|
$3,450
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs