| Assessment Year | 2022 |
|---|---|
| Principal Product | Sporting Goods, Weapons Training |
| NAICS | 451110: Sporting Goods Stores |
| SIC | 5941: Sporting Goods Stores and Bicycle Shops |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
135,000
ft2
|
| Annual Production | 500,000
units
|
| Production Hrs. Annual | 4,380
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $279,214 | 2,091,120 |
kWh
|
$0.13 |
| Natural Gas | $32,813 | 5,073 |
MMBtu
|
$6.47 |
| TOTAL YEARLY COSTS | $312,027 | |||
| RECOMMENDED SAVINGS* | $52,143 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $49,387 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2211: Use optimum temperature | $16,827 | - |
$13,592
104,556
kWh
|
$3,235
-
MMBtu
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $32,030 | $3,319 |
$32,030
240,825
kWh
|
- | |
| 03 | 2.7135: Install occupancy sensors | $697 | $731 |
$697
5,242
kWh
|
- | |
| 04 | 2.7134: Use photocell controls | $305 | $507 |
$305
2,296
kWh
|
- | |
| 05 | 2.7444: Close holes and openings in building such as broken windows | $530 | $62 |
$530
4,079
kWh
|
- | |
| 06 | 2.6211: Conserve energy by efficient use of vending machines | $816 | $410 |
$816
6,279
kWh
|
- | |
| 07 | 2.2136: Install / repair insulation on steam lines | $188 | $81 | - |
$188
-
MMBtu
|
|
| 08 | 2.7291: Reschedule and rearrange multiple-source heating systems | $749 | $130 |
$749
5,760
kWh
|
- | |
| TOTAL RECOMMENDED | $52,143 | $5,240 |
$48,720
369,037
kWh
|
$3,423
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $49,387 | $3,381 |
$46,152
349,460
kWh
|
$3,235
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs