Assessment Year | 2025 |
---|---|
Principal Product | aluminum products |
NAICS | 332313: Plate Work Manufacturing |
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $100 M to 500M |
# of Employees | 300 |
Plant Area |
320,000
ft2
|
Annual Production | 30,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $466,063 | 10,260,908 |
kWh
|
$0.045 |
Electricity Demand | $515,379 | 21,731 |
kW-mo/yr
|
$23.72 |
Electricity Fees | $50,582 | - |
|
- |
Natural Gas | $66,866 | 47,021 |
MMBtu
|
$1.42 |
Other Gas | $44,573 | 1 |
MMBtu
|
$44,573.00 |
TOTAL YEARLY COSTS | $1,143,463 | |||
RECOMMENDED SAVINGS* | $29,796 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3132: Recharge batteries on during off-peak demand periods | $13,036 | $2,070 |
$741
74,131
kWh
|
$12,294
-
kW-mo/yr
|
- | |
02 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $8,641 | $62,943 | - | - |
$8,641
-
MMBtu
|
|
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,424 | $4,121 |
$53
1,166
kWh
|
$461
-
kW-mo/yr
|
$2,910
-
MMBtu
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $57 | $80 |
$33
736
kWh
|
$24
-
kW-mo/yr
|
- | |
05 | 2.6125: Keep equipment clean | $1,593 | - |
$795
17,503
kWh
|
$798
-
kW-mo/yr
|
- | |
06 | 2.7224: Reduce space conditioning during non-working hours | $1,230 | - |
$266
3,278
kWh
|
$915
-
kW-mo/yr
|
$50
-
MMBtu
|
|
07 | 2.7496: Install partitions to reduce size of conditioned space | $1,816 | $2,353 |
$237
5,269
kWh
|
$1,579
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $29,796 | $71,567 |
$2,125
102,083
kWh
|
$16,071
-
kW-mo/yr
|
$11,600
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs