ITAC Assessment: LE0457
ITAC logo
ITAC Assessment: LE0457
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Laminated vinyl
NAICS 313320: Fabric Coating Mills
SIC 2295: Coated Fabrics, Not Rubberized
Sales Range $10
M
to 50
M
# of Employees 45
Plant Area 160,000
ft2
Annual Production 26,941,227
thousand feet
Production Hrs. Annual 6,240
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $213,445 3,022,125
kWh
Electricity Demand $30,496 7,569
kW-mo/yr
Electricity Fees $29,124 -
Natural Gas $169,383 22,505
MMBtu
TOTAL YEARLY COSTS $442,448
RECOMMENDED SAVINGS* $53,862 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,471

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $9,554 $25,157 $7,841
110,430
kWh
$1,713
-
kW-mo/yr
-
02 2.4221: Install compressor air intakes in coolest locations $619 $2,200 $534
7,524
kWh
$85
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,771 $10,041 $2,086
29,384
kWh
$685
-
kW-mo/yr
-
04 2.1224: Replace boiler $33,772 $150,000 - - $33,772
-
MMBtu
05 2.7232: Replace existing hvac unit with high efficiency model $2,689 $13,000 $2,405
33,869
kWh
$284
-
kW-mo/yr
-
06 2.4226: Use / purchase optimum sized compressor $4,457 $36,000 $4,018
56,591
kWh
$439
-
kW-mo/yr
-
TOTAL RECOMMENDED $53,862 $236,398 $16,884
237,798
kWh
$3,206
-
kW-mo/yr
$33,772
-
MMBtu
TOTAL IMPLEMENTED $19,471 $84,198 $16,350
230,274
kWh
$3,121
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs