| Assessment Year | 2024 |
|---|---|
| Principal Product | Machined metal parts |
| NAICS | 332710: Machine Shops |
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 150 |
| Plant Area |
121,000
ft2
|
| Annual Production | 2,400,000
units
|
| Production Hrs. Annual | 4,810
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $58,210 | 1,136,500 |
kWh
|
$0.051 |
| Electricity Demand | $99,711 | 2,909 |
kW-mo/yr
|
$34.28 |
| Natural Gas | $11,296 | 1,121 |
MMBtu
|
$10.08 |
| TOTAL YEARLY COSTS | $169,217 | |||
| RECOMMENDED SAVINGS* | $4,209 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,133 | - |
$868
17,363
kWh
|
$1,265
-
kW-mo/yr
|
- | |
| 02 | 2.6218: Turn off equipment when not in use | $717 | $700 |
$265
5,291
kWh
|
$453
-
kW-mo/yr
|
- | |
| 03 | 2.6218: Turn off equipment when not in use | $7 | $24 |
$4
78
kWh
|
$3
-
kW-mo/yr
|
- | |
| 04 | 2.7124: Make a practice of turning off lights when not needed | $49 | - |
$18
356
kWh
|
$31
-
kW-mo/yr
|
- | |
| 05 | 2.7134: Use photocell controls | $191 | $248 |
$99
1,971
kWh
|
$93
-
kW-mo/yr
|
- | |
| 06 | 2.7135: Install occupancy sensors | $236 | $62 |
$87
1,746
kWh
|
$149
-
kW-mo/yr
|
- | |
| 07 | 2.7261: Install timers and/or thermostats | $625 | $600 | - | - |
$625
-
MMBtu
|
|
| 08 | 2.7492: Use proper thickness of insulation on building envelope | $251 | $144 | - | - |
$251
-
MMBtu
|
|
| TOTAL RECOMMENDED | $4,209 | $1,778 |
$1,340
26,805
kWh
|
$1,993
-
kW-mo/yr
|
$876
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs