ITAC Assessment: MU0045
ITAC logo
ITAC Assessment: MU0045
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product axle shafts
NAICS 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $100
M
to 500
M
# of Employees 320
Plant Area 100,000
ft2
Annual Production 2,260,700
units
Production Hrs. Annual 6,240
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,271,805 14,344,797
kWh
Electricity Demand $177,295 34,483
kW-mo/yr
Electricity Fees $26,988 -
Natural Gas $221,605 30,259
MMBtu
Waste Disposal Costs
Water Usage $33,174 1,249
Tgal
Water Disposal $29,929 1,249
Tgal
TOTAL YEARLY COSTS $1,760,796
RECOMMENDED SAVINGS* $204,232 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Primary Product Savings
01 2.3132: Recharge batteries on during off-peak demand periods $1,629 - - $1,244
-
kW-mo/yr
- - - $385
02 2.3212: Optimize plant power factor $14,981 $56,840 - - - - - $14,981
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $31,005 $34,270 $26,026
289,182
kWh
$4,978
-
kW-mo/yr
- - - -
04 2.4322: Use or replace with energy efficient substitutes $7,936 $18,703 $7,151
79,456
kWh
$785
-
kW-mo/yr
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,606 $17 $2,348
26,094
kWh
$258
-
kW-mo/yr
- - - -
06 2.6218: Turn off equipment when not in use $5,088 - $4,521
50,232
kWh
$567
-
kW-mo/yr
- - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,694 $706 $1,310
14,560
kWh
$384
-
kW-mo/yr
- - - -
08 2.7221: Lower temperature during the winter season and vice-versa $2,871 - - - $2,871
-
MMBtu
- - -
09 2.7447: Install vinyl strip / high speed / air curtain doors $38,860 $12,105 $(-510.3)
(-5,670)
kWh
$(-332.0)
-
kW-mo/yr
$39,702
-
MMBtu
- - -
10 2.7492: Use proper thickness of insulation on building envelope $5,014 $4,165 - - $5,014
-
MMBtu
- - -
11 2.7496: Install partitions to reduce size of conditioned space $1,256 $1,302 - - $1,256
-
MMBtu
- - -
12 3.4151: Minimize water usage $25,914 $8,239 - - - $13,623
-
Tgal
$12,291
-
Tgal
-
13 3.4151: Minimize water usage $60,609 $146,420 - - - - - $60,609
14 4.821: Pay bills on time to avoid late fees $4,768 - - - - - - $4,768
TOTAL RECOMMENDED $204,232 $282,768 $40,847
453,854
kWh
$7,884
-
kW-mo/yr
$48,843
-
MMBtu
$13,623
-
Tgal
$12,291
-
Tgal
$80,743
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs