ITAC Assessment: MU0030
ITAC logo
ITAC Assessment: MU0030
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product they build miscellaneous fabricated metal products
NAICS 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 100,000
ft2
Annual Production 4,680,000
lb
Production Hrs. Annual 5,304
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $57,573 708,033
kWh
Electricity Demand $67,426 3,585
kW-mo/yr
Electricity Fees $9,262 -
Natural Gas $47,920 5,364
MMBtu
TOTAL YEARLY COSTS $182,181
RECOMMENDED SAVINGS* $12,449 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,449

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,029 $1,089 $2,630
32,876
kWh
$1,399
-
kW-mo/yr
- -
02 2.7134: Use photocell controls $110 $495 $110
1,373
kWh
- - -
03 2.7135: Install occupancy sensors $205 $472 $205
2,562
kWh
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $227 $374 $172
2,146
kWh
$55
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $964 $3,110 $964
12,051
kWh
- - -
06 2.7224: Reduce space conditioning during non-working hours $1,540 - $180
2,246
kWh
$56
-
kW-mo/yr
- $1,304
-
MMBtu
07 2.7444: Close holes and openings in building such as broken windows $214 $450 - - - $214
-
MMBtu
08 2.7447: Install vinyl strip / high speed / air curtain doors $2,497 $11,600 - - - $2,497
-
MMBtu
09 2.7492: Use proper thickness of insulation on building envelope $63 $166 - - - $63
-
MMBtu
10 2.7492: Use proper thickness of insulation on building envelope $229 $375 - - - $229
-
MMBtu
11 2.7492: Use proper thickness of insulation on building envelope $766 $1,942 - - - $766
-
MMBtu
12 2.8121: Apply for tax-free status for energy purchases $1,604 - - - $1,604 -
TOTAL RECOMMENDED $12,449 $20,073 $4,261
53,254
kWh
$1,511
-
kW-mo/yr
$1,604 $5,073
-
MMBtu
TOTAL IMPLEMENTED $12,449 $20,073 $4,261
53,254
kWh
$1,511
-
kW-mo/yr
$1,604 $5,073
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs