Assessment Year | 2023 |
---|---|
Principal Product | they build miscellaneous fabricated metal products |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
100,000
ft2
|
Annual Production | 4,680,000
lb
|
Production Hrs. Annual | 5,304
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $57,573 | 708,033 |
kWh
|
$0.081 |
Electricity Demand | $67,426 | 3,585 |
kW-mo/yr
|
$18.81 |
Electricity Fees | $9,262 | - |
|
- |
Natural Gas | $47,920 | 5,364 |
MMBtu
|
$8.93 |
TOTAL YEARLY COSTS | $182,181 | |||
RECOMMENDED SAVINGS* | $12,449 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,449 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,029 | $1,089 |
$2,630
32,876
kWh
|
$1,399
-
kW-mo/yr
|
- | - | |
02 | 2.7134: Use photocell controls | $110 | $495 |
$110
1,373
kWh
|
- | - | - | |
03 | 2.7135: Install occupancy sensors | $205 | $472 |
$205
2,562
kWh
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $227 | $374 |
$172
2,146
kWh
|
$55
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $964 | $3,110 |
$964
12,051
kWh
|
- | - | - | |
06 | 2.7224: Reduce space conditioning during non-working hours | $1,540 | - |
$180
2,246
kWh
|
$56
-
kW-mo/yr
|
- |
$1,304
-
MMBtu
|
|
07 | 2.7444: Close holes and openings in building such as broken windows | $214 | $450 | - | - | - |
$214
-
MMBtu
|
|
08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,497 | $11,600 | - | - | - |
$2,497
-
MMBtu
|
|
09 | 2.7492: Use proper thickness of insulation on building envelope | $63 | $166 | - | - | - |
$63
-
MMBtu
|
|
10 | 2.7492: Use proper thickness of insulation on building envelope | $229 | $375 | - | - | - |
$229
-
MMBtu
|
|
11 | 2.7492: Use proper thickness of insulation on building envelope | $766 | $1,942 | - | - | - |
$766
-
MMBtu
|
|
12 | 2.8121: Apply for tax-free status for energy purchases | $1,604 | - | - | - | $1,604 | - | |
TOTAL RECOMMENDED | $12,449 | $20,073 |
$4,261
53,254
kWh
|
$1,511
-
kW-mo/yr
|
$1,604 |
$5,073
-
MMBtu
|
||
TOTAL IMPLEMENTED | $12,449 | $20,073 |
$4,261
53,254
kWh
|
$1,511
-
kW-mo/yr
|
$1,604 |
$5,073
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs