ITAC Assessment: MU0028
ITAC logo
ITAC Assessment: MU0028
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Hydraulic Oil Filters and Components
NAICS 333999: All Other Miscellaneous General Purpose Machinery Manufacturing
SIC 3569: General Industrial Machinery and Equipment, Not Elsewhere
Sales Range $50
M
to 100
M
# of Employees 130
Plant Area 115,000
ft2
Annual Production 1,500,000
units
Production Hrs. Annual 6,552
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $201,007 2,340,147
kWh
Electricity Demand $101,278 5,985
kW-mo/yr
Electricity Fees $(-8,940.5) -
Natural Gas $23,139 2,694
MMBtu
TOTAL YEARLY COSTS $316,483
RECOMMENDED SAVINGS* $8,110 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,749

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,186 - $1,186
13,789
kWh
- -
02 2.6218: Turn off equipment when not in use $2,322 - $2,322
27,003
kWh
- -
03 2.7111: Reduce illumination to minimum necessary levels $1,919 - $1,841
21,406
kWh
$78
-
kW-mo/yr
-
04 2.7134: Use photocell controls $138 $348 $138
1,606
kWh
- -
05 2.7135: Install occupancy sensors $863 $112 $863
10,031
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $643 $1,100 $643
7,477
kWh
- -
07 2.7447: Install vinyl strip / high speed / air curtain doors $550 $776 $550
6,396
kWh
- -
08 2.7492: Use proper thickness of insulation on building envelope $490 $1,162 - - $490
-
MMBtu
TOTAL RECOMMENDED $8,110 $3,498 $7,543
87,708
kWh
$78
-
kW-mo/yr
$490
-
MMBtu
TOTAL IMPLEMENTED $4,749 $1,560 $4,671
54,309
kWh
$78
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs