Assessment Year | 2023 |
---|---|
Principal Product | they build assembly line machinery |
NAICS | 333519: Rolling Mill and Other Metalworking Machinery Manufacturing |
SIC | 3549: Metalworking Machinery, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 350 |
Plant Area |
500,000
ft2
|
Annual Production | 58
units
|
Production Hrs. Annual | 4,416
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $115,015 | 2,505,600 |
kWh
|
$0.046 |
Electricity Demand | $85,737 | 5,008 |
kW-mo/yr
|
$17.12 |
Electricity Fees | $49,625 | - |
|
- |
Natural Gas | $368,849 | 44,349 |
MMBtu
|
$8.32 |
TOTAL YEARLY COSTS | $619,226 | |||
RECOMMENDED SAVINGS* | $151,790 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $127,763 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $18,370 | $6,347 |
$12,015
240,300
kWh
|
$6,355
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $905 | $133 |
$469
9,382
kWh
|
$436
-
kW-mo/yr
|
- | - | |
03 | 2.6218: Turn off equipment when not in use | $101,263 | - | - | - | - |
$101,263
-
MMBtu
|
|
04 | 2.7111: Reduce illumination to minimum necessary levels | $181 | - |
$123
2,460
kWh
|
$58
-
kW-mo/yr
|
- | - | |
05 | 2.7134: Use photocell controls | $88 | $349 |
$88
1,750
kWh
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $419 | $1,650 |
$285
5,694
kWh
|
$134
-
kW-mo/yr
|
- | - | |
07 | 2.7221: Lower temperature during the winter season and vice-versa | $4,405 | - |
$1,123
22,466
kWh
|
$336
-
kW-mo/yr
|
- |
$2,946
-
MMBtu
|
|
08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $23,547 | $85,720 |
$(-805.0)
16,099
kWh
|
- | - |
$24,352
-
MMBtu
|
|
09 | 2.7492: Use proper thickness of insulation on building envelope | $211 | $522 | - | - | - |
$211
-
MMBtu
|
|
10 | 2.8121: Apply for tax-free status for energy purchases | $2,402 | - | - | - | $2,402 | - | |
TOTAL RECOMMENDED | $151,790 | $94,721 |
$13,298
298,151
kWh
|
$7,319
-
kW-mo/yr
|
$2,402 |
$128,772
-
MMBtu
|
||
TOTAL IMPLEMENTED | $127,763 | $8,130 |
$13,892
277,842
kWh
|
$7,261
-
kW-mo/yr
|
$2,402 |
$104,209
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs