Assessment Year | 2023 |
---|---|
Principal Product | Tooling products and manufacturing equipment |
NAICS | 333519: Rolling Mill and Other Metalworking Machinery Manufacturing |
SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
55,000
ft2
|
Annual Production | 8,000
units
|
Production Hrs. Annual | 4,940
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $110,230 | 715,800 |
kWh
|
$0.15 |
Electricity Fees | $657 | - |
|
- |
Natural Gas | $10,654 | 1,254 |
MMBtu
|
$8.50 |
TOTAL YEARLY COSTS | $121,541 | |||
RECOMMENDED SAVINGS* | $27,054 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,001 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2211: Use optimum temperature | $321 | - | - | - |
$321
-
MMBtu
|
|
02 | 2.4133: Use most efficient type of electric motors | $147 | $683 |
$147
982
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $754 | $320 |
$754
5,028
kWh
|
- | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $24 | $24 |
$24
161
kWh
|
- | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $62 | $71 |
$62
416
kWh
|
- | - | |
06 | 2.7135: Install occupancy sensors | $76 | $71 |
$76
504
kWh
|
- | - | |
07 | 2.8121: Apply for tax-free status for energy purchases | $1,775 | $1,183 | - | $1,775 | - | |
08 | 4.452: Eliminate shift | $23,894 | - |
$23,894
159,293
kWh
|
- | - | |
TOTAL RECOMMENDED | $27,054 | $2,352 |
$24,957
166,383
kWh
|
$1,775 |
$321
-
MMBtu
|
||
TOTAL IMPLEMENTED | $1,001 | $1,097 |
$1,001
6,674
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs