Assessment Year | 2000 |
---|---|
Principal Product | Paper Industry Machinery |
NAICS |
n/a
|
SIC | 3554: Paper Industries Machinery |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
200,000
ft2
|
Annual Production | 3,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $151,846 | 4,842,321 |
kWh
|
$0.031 |
Electricity Demand | $149,847 | 27,283 |
kW-mo/yr
|
$5.49 |
Electricity Fees | $96,493 | - |
|
- |
Natural Gas | $100,238 | 24,510 |
MMBtu
|
$4.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,071 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $31,041 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,633 | $18,330 |
$3,996
127,198
kWh
|
$2,637
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $2,714 | $5,000 |
$2,714
86,460
kWh
|
- | - | |
03 | 2.7134: Use photocell controls | $3,386 | $1,515 |
$3,386
107,855
kWh
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,271 | $1,500 |
$743
23,740
kWh
|
$528
-
kW-mo/yr
|
- | |
05 | 2.4226: Use / purchase optimum sized compressor | $7,030 | $9,000 |
$7,030
37,222
kWh
|
- | - | |
06 | 2.7243: Improve air circulation with destratification fans / other methods | $13,935 | $8,000 | - | - |
$13,935
-
MMBtu
|
|
07 | 2.2136: Install / repair insulation on steam lines | $3,102 | $4,641 | - | - |
$3,102
-
MMBtu
|
|
TOTAL RECOMMENDED | $38,071 | $47,986 |
$17,869
382,475
kWh
|
$3,165
-
kW-mo/yr
|
$17,037
-
MMBtu
|
||
TOTAL IMPLEMENTED | $31,041 | $38,986 |
$10,839
345,253
kWh
|
$3,165
-
kW-mo/yr
|
$17,037
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs