Assessment Year | 2000 |
---|---|
Principal Product | Cutting Tool Manufacture and Repair |
NAICS |
n/a
|
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 50 |
Plant Area |
23,000
ft2
|
Annual Production | 33,480
pieces
|
Production Hrs. Annual | 5,408
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $23,972 | 572,098 |
kWh
|
$0.042 |
Electricity Demand | $10,884 | 1,932 |
kW-mo/yr
|
$5.63 |
Electricity Fees | $2,004 | - |
|
- |
Natural Gas | $7,465 | 1,396 |
MMBtu
|
$5.35 |
LPG | $207 | 17 |
MMBtu
|
$12.18 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,248 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,756 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,330 | $7,355 |
$1,740
41,325
kWh
|
$590
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.3212: Optimize plant power factor | $1,323 | $1,050 | - | - | $1,323 | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,603 | $180 |
$1,200
28,722
kWh
|
$403
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7261: Install timers and/or thermostats | $1,142 | $2,040 | - | - | - |
$1,142
-
MMBtu
|
- | - | |
05 | 2.2437: Recover waste heat from equipment | $758 | $1,130 | - | - | - |
$758
-
MMBtu
|
- | - | |
06 | 3.6124: Burn waste oil for heat | $1,329 | $3,495 |
$(-74.0)
(-1,758)
kWh
|
- | - |
$494
-
MMBtu
|
$1,260
-
gal
|
$(-351.0) | |
07 | 4.441: Install automatic packing equipment | $1,560 | $3,000 | - | - | - | - | - | $1,560 | |
08 | 4.611: Begin a practice of predictive / preventative maintenance | $1,203 | - | - | - | - | - | - | $1,203 | |
TOTAL RECOMMENDED | $11,248 | $18,250 |
$2,866
68,289
kWh
|
$993
-
kW-mo/yr
|
$1,323 |
$2,394
-
MMBtu
|
$1,260
-
gal
|
$2,412 | ||
TOTAL IMPLEMENTED | $6,756 | $11,575 |
$1,740
41,325
kWh
|
$590
-
kW-mo/yr
|
$1,323 |
$1,900
-
MMBtu
|
- | $1,203 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs