Assessment Year | 2022 |
---|---|
Principal Product | Plastic Automotive Parts |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3711: Motor Vehicles and Passenger Car Bodies |
Sales Range | $50 M to 100M |
# of Employees | 400 |
Plant Area |
300,000
ft2
|
Annual Production | 46,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,040,344 | 12,168,564 |
kWh
|
$0.085 |
Electricity Demand | $22,376 | 31,478 |
kW-mo/yr
|
$0.71 |
Electricity Fees | $27,143 | - |
|
- |
Natural Gas | $117,625 | 37,214 |
MMBtu
|
$3.16 |
TOTAL YEARLY COSTS | $1,207,487 | |||
RECOMMENDED SAVINGS* | $20,913 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $51 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $7,823 | $5,216 | - | - | $7,823 | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $781 | $1,484 |
$773
8,585
kWh
|
$8
-
kW-mo/yr
|
- | - | |
03 | 2.3212: Optimize plant power factor | $5,232 | $12,600 | - | - | $5,232 | - | |
04 | 2.7243: Improve air circulation with destratification fans / other methods | $5,761 | $27,719 | - | - | - |
$5,761
-
MMBtu
|
|
05 | 2.7111: Reduce illumination to minimum necessary levels | $202 | - |
$202
2,247
kWh
|
- | - | - | |
06 | 2.7442: Keep doors and windows shut when not on use | $51 | $30 |
$33
367
kWh
|
- | - |
$18
-
MMBtu
|
|
07 | 2.7492: Use proper thickness of insulation on building envelope | $1,062 | $6,845 | - | - | - |
$1,062
-
MMBtu
|
|
TOTAL RECOMMENDED | $20,913 | $53,894 |
$1,008
11,199
kWh
|
$8
-
kW-mo/yr
|
$13,056 |
$6,841
-
MMBtu
|
||
TOTAL IMPLEMENTED | $51 | $30 |
$33
367
kWh
|
- | - |
$18
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs