ITAC Assessment: MU0007
ITAC logo
ITAC Assessment: MU0007
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Automotive Circuit Boards
NAICS 335931: Current-Carrying Wiring Device Manufacturing
SIC 3643: Current-Carrying Wiring Devices
Sales Range $100
M
to 500
M
# of Employees 670
Plant Area 280,000
ft2
Annual Production 106,000,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $555,196 13,209,600
kWh
Electricity Demand $661,009 24,874
kW-mo/yr
Natural Gas $57,037 9,353
MMBtu
TOTAL YEARLY COSTS $1,273,242
RECOMMENDED SAVINGS* $40,159 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,347

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $18,417 $10,160 $7,874
196,842
kWh
$10,543
-
kW-mo/yr
-
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $18,200 $7,825 $12,542
313,544
kWh
$5,659
-
kW-mo/yr
-
03 2.7111: Reduce illumination to minimum necessary levels $1,914 - $840
21,010
kWh
$1,074
-
kW-mo/yr
-
04 3.1191: Change procedures / equipment / operating conditions $1,004 - $61
1,528
kWh
- $943
-
MMBtu
05 2.6232: Install set-back timers $612 $541 $515
12,863
kWh
- $98
-
MMBtu
06 2.7444: Close holes and openings in building such as broken windows $12 $44 $2
46
kWh
- $10
-
MMBtu
TOTAL RECOMMENDED $40,159 $18,571 $21,833
545,833
kWh
$17,275
-
kW-mo/yr
$1,051
-
MMBtu
TOTAL IMPLEMENTED $21,347 $10,204 $8,777
219,426
kWh
$11,616
-
kW-mo/yr
$953
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs