ITAC Assessment: MU0001
ITAC logo
ITAC Assessment: MU0001
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Wood chippers
NAICS 333120: Construction Machinery Manufacturing
SIC 3531: Construction Machinery and Equipment
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 1,300,000
ft2
Annual Production 7,000
ton
Production Hrs. Annual 8,760
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $362,014 6,514,506
kWh
Electricity Demand $112,292 16,760
kW-mo/yr
Natural Gas $182,147 57,373
MMBtu
TOTAL YEARLY COSTS $656,453
RECOMMENDED SAVINGS* $18,179 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,610

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,472 - $1,755
29,255
kWh
$1,717
-
kW-mo/yr
-
02 2.7446: Utilize sensors controlling roof and wall openings $2,156 $3,960 $2,156
35,927
kWh
- -
03 2.7311: Ventilation system to shut off when room is not in use $2,694 $600 $2,694
44,906
kWh
- -
04 2.1212: Operate boilers on high fire setting $2,532 $146 - - $2,532
-
MMBtu
05 2.7444: Close holes and openings in building such as broken windows $7,097 $16,000 - - $7,097
-
MMBtu
06 2.6218: Turn off equipment when not in use $228 - $228
3,804
kWh
- -
TOTAL RECOMMENDED $18,179 $20,706 $6,833
113,891
kWh
$1,717
-
kW-mo/yr
$9,629
-
MMBtu
TOTAL IMPLEMENTED $7,610 $4,706 $5,078
84,637
kWh
- $2,532
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs