| Assessment Year | 2026 |
|---|---|
| Principal Product | Tie Rods/Struts |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 119 |
| Plant Area |
110,000
ft2
|
| Annual Production | 181,000
pieces
|
| Production Hrs. Annual | 7,072
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $175,282 | 2,000,000 |
kWh
|
$0.088 |
| Electricity Demand | $27,397 | 3,915 |
kW-mo/yr
|
$7.00 |
| Electricity Fees | $17,321 | - |
|
- |
| Natural Gas | $64,504 | 7,000 |
MMBtu
|
$9.21 |
| Other Gas | $5,496 | 1 |
MMBtu
|
$5,496.00 |
| TOTAL YEARLY COSTS | $290,000 | |||
| RECOMMENDED SAVINGS* | $15,614 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4226: Use / purchase optimum sized compressor | $5,694 | $55,158 |
$5,005
57,138
kWh
|
$689
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,097 | $13,445 |
$1,843
21,043
kWh
|
$254
-
kW-mo/yr
|
- | |
| 03 | 2.7135: Install occupancy sensors | $6,789 | $3,326 |
$6,789
77,501
kWh
|
- | - | |
| 04 | 2.3212: Optimize plant power factor | $1,034 | $3,395 | - | - | $1,034 | |
| TOTAL RECOMMENDED | $15,614 | $75,324 |
$13,637
155,682
kWh
|
$943
-
kW-mo/yr
|
$1,034 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs