| Assessment Year | 2026 |
|---|---|
| Principal Product | Metal Seat Frames |
| NAICS | 336370: Motor Vehicle Metal Stamping |
| SIC | 3465: Automotive Stampings |
| Sales Range | $100 M to 500M |
| # of Employees | 625 |
| Plant Area |
425,278
ft2
|
| Annual Production | 34,000,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $827,387 | 10,339,604 |
kWh
|
$0.080 | |
| Electricity Demand | $265,821 | 21,511 |
kW-mo/yr
|
$12.36 | |
| Electricity Fees | $12,203 | - |
|
- | |
| Natural Gas | $48,420 | 5,320 |
MMBtu
|
$9.10 | |
| Waste Disposal Costs | |||||
| Water Usage | $5,347 | 1,330 |
Tgal
|
$4.02 | |
| Water Disposal | $8,182 | 1,302 |
Tgal
|
$6.28 | |
| TOTAL YEARLY COSTS | $1,167,360 | ||||
| RECOMMENDED SAVINGS* | $143,763 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,542 | $4,076 |
$8,542
106,778
kWh
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $43,920 | $18,347 |
$43,920
548,991
kWh
|
- | |
| 03 | 2.7232: Replace existing hvac unit with high efficiency model | $7,757 | $94,500 |
$7,175
89,685
kWh
|
$582
-
kW-mo/yr
|
|
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $523 | - |
$523
6,547
kWh
|
- | |
| 05 | 4.721: Initiate a program to acquire iso certification | $82,739 | $1,000 |
$82,739
1,034,238
kWh
|
- | |
| 06 | 2.7135: Install occupancy sensors | $282 | $1,277 |
$282
3,526
kWh
|
- | |
| TOTAL RECOMMENDED | $143,763 | $119,200 |
$143,181
1,789,765
kWh
|
$582
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs