| Assessment Year | 2026 |
|---|---|
| Principal Product | Engine Components |
| NAICS | 333618: Other Engine Equipment Manufacturing |
| SIC | 3519: Internal Combustion Engines, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 415 |
| Plant Area |
794,094
ft2
|
| Annual Production | 100,000
units
|
| Production Hrs. Annual | 2,500
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $653,313 | 11,262,955 |
kWh
|
$0.058 | |
| Electricity Demand | $275,003 | 27,735 |
kW-mo/yr
|
$9.92 | |
| Electricity Fees | $80,862 | - |
|
- | |
| Natural Gas | $41,531 | 3,398 |
MMBtu
|
$12.22 | |
| Waste Disposal Costs | |||||
| Water Usage | $35,584 | 5,862 |
Tgal
|
$6.07 | |
| Water Disposal | $35,584 | 5,862 |
Tgal
|
$6.07 | |
| TOTAL YEARLY COSTS | $1,121,877 | ||||
| RECOMMENDED SAVINGS* | $43,088 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,030 | $2,244 |
$8,030
138,448
kWh
|
- | |
| 02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $5,879 | $1,680 |
$5,879
101,367
kWh
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $10,936 | - |
$10,936
188,549
kWh
|
- | |
| 04 | 2.3212: Optimize plant power factor | $18,243 | $121,000 | - |
$18,243
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $43,088 | $124,924 |
$24,845
428,364
kWh
|
$18,243
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs