ITAC Assessment: MS0355
ITAC logo
ITAC Assessment: MS0355
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product CABLE PRODUCTS
NAICS 335929: Other Communication and Energy Wire Manufacturing
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $100
M
to 500
M
# of Employees 63
Plant Area 218,785
ft2
Annual Production 6,000
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $108,310 2,304,426
kWh
Electricity Demand $23,663 7,394
kW-mo/yr
Electricity Fees $22,273 -
Natural Gas $34,726 4,021
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $54,841 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $31,176 $44,540 $24,731
511,971
kWh
$3,611
-
kW-mo/yr
$2,834
02 2.4131: Size electric motors for peak operating efficiency $10,766 $6,978 $8,874
183,717
kWh
$993
-
kW-mo/yr
$899
03 2.4226: Use / purchase optimum sized compressor $7,078 $32,037 $5,522
114,306
kWh
$891
-
kW-mo/yr
$665
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,361 $32,037 $2,696
55,822
kWh
- $665
05 2.7232: Replace existing hvac unit with high efficiency model $1,377 $59,145 $1,302
26,952
kWh
- $75
06 2.7142: Utilize higher efficiency lamps and/or ballasts $793 $6,281 $526
10,883
kWh
$170
-
kW-mo/yr
$97
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $290 $595 $239
4,942
kWh
$27
-
kW-mo/yr
$24
TOTAL RECOMMENDED $54,841 $181,613 $43,890
908,593
kWh
$5,692
-
kW-mo/yr
$5,259
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs