ITAC Assessment: MS0294
ITAC logo
ITAC Assessment: MS0294
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product copper tubing
NAICS 331420: Copper Rolling, Drawing, Extruding, and Alloying
SIC 3351: Rolling, Drawing, and Extruding Of Copper
Sales Range $100
M
to 500
M
# of Employees 370
Plant Area 420,000
ft2
Annual Production 220,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,478,582 57,293,550
kWh
Electricity Demand $1,144,460 106,855
kW-mo/yr
Electricity Fees $72,266 -
Natural Gas $5,434,615 59,357
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $157,273 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,000

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.3412: Use waste heat to produce steam to drive a steam turbine-generator $93,222 $290,000 $56,522
2,102,755
kWh
$35,322
-
kW-mo/yr
$1,378
02 2.7142: Utilize higher efficiency lamps and/or ballasts $47,448 $70,420 $30,781
1,145,111
kWh
$15,966
-
kW-mo/yr
$701
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $11,175 $21,180 $11,010
409,602
kWh
- $165
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,047 $10,811 $1,062
39,524
kWh
$954
-
kW-mo/yr
$31
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,760 $172 $1,734
64,527
kWh
- $26
06 2.4221: Install compressor air intakes in coolest locations $1,240 $609 $704
26,208
kWh
$518
-
kW-mo/yr
$18
07 2.7229: Air condition only space necessary $381 $240 $111
4,147
kWh
$264
-
kW-mo/yr
$6
TOTAL RECOMMENDED $157,273 $393,432 $101,924
3,791,874
kWh
$53,024
-
kW-mo/yr
$2,325
TOTAL IMPLEMENTED $3,000 $781 $2,438
90,735
kWh
$518
-
kW-mo/yr
$44
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs