ITAC Assessment: MA0357
ITAC logo
ITAC Assessment: MA0357
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Injection molded utensils and containers
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 188
Plant Area 166,000
ft2
Annual Production 14
ton
Production Hrs. Annual 8,760
hrs
Location (State) New Hampshire

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,499,683 18,773,154
kWh
Electricity Demand $257,011 32,910
kW-mo/yr
Electricity Fees $6,085 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $98,307 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Other Liquid (non-haz) Savings
01 2.4322: Use or replace with energy efficient substitutes $72,723 $72,500 $72,723
910,610
kWh
-
02 3.5111: Filter and reuse hydraulic oil $13,997 $734 - $13,997
-
gal
03 2.4314: Use synthetic lubricant $6,765 $1,200 $6,765
84,701
kWh
-
04 2.4224: Upgrade controls on compressors $4,822 $6,000 $4,822
60,375
kWh
-
TOTAL RECOMMENDED $98,307 $80,434 $84,310
1,055,686
kWh
$13,997
-
gal
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs