ITAC Assessment: UA0116
ITAC logo
ITAC Assessment: UA0116
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Lumber
NAICS 321113: Sawmills
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area 342,000
ft2
Annual Production 28,000,000
pieces
Production Hrs. Annual 2,313
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $457,534 5,905,200
kWh
Electricity Fees $26,790 -
Wood $40,000 181,232
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,909 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,367

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Wood Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,740 $5,595 $6,621
85,455
kWh
$119 -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,062 $1,560 $3,990
51,482
kWh
$72 -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,542 $11,972 $9,373
120,976
kWh
$169 -
04 2.1213: Direct warmest air to combustion intake $565 $2,320 - - $565
-
MMBtu
TOTAL RECOMMENDED $20,909 $21,447 $19,984
257,913
kWh
$360 $565
-
MMBtu
TOTAL IMPLEMENTED $11,367 $9,475 $10,611
136,937
kWh
$191 $565
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs