ITAC Assessment: MS0293
ITAC logo
ITAC Assessment: MS0293
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Meat
NAICS 311611: Animal (except Poultry) Slaughtering
SIC 2011: Meat Packing Plants
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area 35,650
ft2
Annual Production 15,000,000
lb
Production Hrs. Annual 4,160
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,842 2,129,300
kWh
Electricity Fees $72,274 -
Natural Gas $144,639 13,312
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,497 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $3,933 $670 - - $3,933
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,385 $176 $361
61,364
kWh
$2,024 -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,307 $2,895 $195
33,627
kWh
$1,112 -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,168 $7,343 $174
30,054
kWh
$994 -
05 3.6124: Burn waste oil for heat $564 $3,595 - - $564
-
MMBtu
06 2.2511: Insulate bare equipment $421 $55 - - $421
-
MMBtu
07 2.7221: Lower temperature during the winter season and vice-versa $351 $210 $52
9,039
kWh
$299 -
08 2.2136: Install / repair insulation on steam lines $235 $62 - - $235
-
MMBtu
09 2.4221: Install compressor air intakes in coolest locations $133 $233 $20
3,422
kWh
$113 -
TOTAL RECOMMENDED $10,497 $15,239 $802
137,506
kWh
$4,542 $5,153
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs