Assessment Year | 2001 |
---|---|
Principal Product | Alumimum forging |
NAICS |
n/a
|
SIC | 3463: Nonferrous Forgings |
Sales Range | $50 M to 100M |
# of Employees | 500 |
Plant Area |
500,000
ft2
|
Annual Production | 4,500,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $249,884 | 3,728,386 |
kWh
|
$0.067 |
Electricity Demand | $139,020 | 11,038 |
kW-mo/yr
|
$12.59 |
Electricity Fees | $26,402 | - |
|
- |
Natural Gas | $1,184,526 | 122,653 |
MMBtu
|
$9.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $3,687,394 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $39,429 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $31,925 | $144,000 |
$28,576
426,507
kWh
|
$3,349
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,393 | $480 |
$9,237
137,861
kWh
|
$3,156
-
kW-mo/yr
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,243 | $6,000 |
$2,770
41,350
kWh
|
$473
-
kW-mo/yr
|
- | - | |
04 | 2.4322: Use or replace with energy efficient substitutes | $8,566 | $5,950 |
$5,868
87,581
kWh
|
$2,698
-
kW-mo/yr
|
- | - | |
05 | 2.7145: Install skylights | $9,916 | $28,500 |
$4,188
62,512
kWh
|
$5,728
-
kW-mo/yr
|
- | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $17,992 | $2,300 |
$13,409
200,130
kWh
|
$4,583
-
kW-mo/yr
|
- | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $9,044 | $18,000 | - | - | - | $9,044 | |
08 | 4.652: Replace existing equipment with more suitable substitutes | $476,943 | $325,000 | - | - | - | $476,943 | |
09 | 4.124: Install continuous lubrication equipment | $385,010 | $152,000 | - | - | $385,010 | - | |
10 | 4.445: Install equipment to move product | $2,622,000 | $180,000 | - | - | $2,622,000 | - | |
11 | 4.651: Install back-up equipment | $110,362 | $400,000 | - | - | - | $110,362 | |
TOTAL RECOMMENDED | $3,687,394 | $1,262,230 |
$64,048
955,941
kWh
|
$19,987
-
kW-mo/yr
|
$3,007,010 | $596,349 | ||
TOTAL IMPLEMENTED | $39,429 | $20,780 |
$22,646
337,991
kWh
|
$7,739
-
kW-mo/yr
|
- | $9,044 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs