ITAC Assessment: MS0228
ITAC logo
ITAC Assessment: MS0228
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Residential and contract furniture
NAICS 337214: Office Furniture (except Wood) Manufacturing
SIC 2522: Office Furniture, Except Wood
Sales Range $50
M
to 100
M
# of Employees 460
Plant Area 562,000
ft2
Annual Production 550,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $404,388 8,781,696
kWh
Electricity Demand $82,493 32,308
kW-mo/yr
Electricity Fees $68,479 -
Natural Gas $310,279 52,118
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,354 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,166

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $4,861 $6,210 - - - $4,861
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,344 $276 $2,283
52,519
kWh
- $61 -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,499 $2,540 $1,017
23,398
kWh
$455
-
kW-mo/yr
$27 -
04 2.4221: Install compressor air intakes in coolest locations $1,237 $1,210 $826
18,993
kWh
$390
-
kW-mo/yr
$21 -
05 2.7221: Lower temperature during the winter season and vice-versa $323 - $315
7,227
kWh
- $8 -
06 2.2511: Insulate bare equipment $90 $157 - - - $90
-
MMBtu
TOTAL RECOMMENDED $10,354 $10,393 $4,441
102,137
kWh
$845
-
kW-mo/yr
$117 $4,951
-
MMBtu
TOTAL IMPLEMENTED $4,166 $2,816 $3,615
83,144
kWh
$455
-
kW-mo/yr
$96 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs