| Assessment Year | 2002 |
|---|---|
| Principal Product | Marin gears |
| NAICS |
n/a
|
| SIC | 3566: Speed Changers, Industrial High-Speed Drives, and Gears |
| Sales Range | $1 M to 5M |
| # of Employees | 50 |
| Plant Area |
45,000
ft2
|
| Annual Production | 2,550
pieces
|
| Production Hrs. Annual | 2,040
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $32,686 | 434,640 |
kWh
|
$0.075 |
| Electricity Demand | $117 | 3,060 |
kW-mo/yr
|
$0.038 |
| Electricity Fees | $7,847 | - |
|
- |
| Natural Gas | $8,426 | 1,155 |
MMBtu
|
$7.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,213 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,523 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $2,023 | $50 | - | - |
$433
-
MMBtu
|
$1,590 | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $1,672 | $1,484 |
$1,421
27,259
kWh
|
$251 | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,018 | $151 |
$865
16,588
kWh
|
$153 | - | - | |
| 04 | 2.7261: Install timers and/or thermostats | $500 | $708 |
$425
8,154
kWh
|
$75 | - | - | |
| TOTAL RECOMMENDED | $5,213 | $2,393 |
$2,711
52,001
kWh
|
$479 |
$433
-
MMBtu
|
$1,590 | ||
| TOTAL IMPLEMENTED | $2,523 | $758 |
$425
8,154
kWh
|
$75 |
$433
-
MMBtu
|
$1,590 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs