| Assessment Year | 2002 |
|---|---|
| Principal Product | Industrial lifting equipment |
| NAICS |
n/a
|
| SIC | 3537: Industrial Trucks, Tractors, Trailers, and Stackers |
| Sales Range | $50 M to 100M |
| # of Employees | 513 |
| Plant Area |
474,000
ft2
|
| Annual Production | 450
pieces
|
| Production Hrs. Annual | 7,000
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $247,968 | 7,166,700 |
kWh
|
$0.035 |
| Electricity Demand | $194,314 | 18,297 |
kW-mo/yr
|
$10.62 |
| Electricity Fees | $6,719 | - |
|
- |
| Natural Gas | $189,608 | 38,024 |
MMBtu
|
$4.99 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $92,238 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $41,542 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.6212: Turn off equipment during breaks, reduce operating time | $26,748 | $7,400 | - | - | - |
$26,748
-
MMBtu
|
- | - | - | |
| 02 | 2.3191: Use demand controller or load shedder | $6,371 | $11,500 | - |
$6,276
-
kW-mo/yr
|
$95 | - | - | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,766 | $288 |
$3,708
107,175
kWh
|
- | $58 | - | - | - | - | |
| 04 | 2.7261: Install timers and/or thermostats | $3,765 | $3,400 |
$3,709
107,201
kWh
|
- | $56 | - | - | - | - | |
| 05 | 2.7144: Install spectral reflectors / delamp | $2,288 | $270 |
$995
28,760
kWh
|
$1,260
-
kW-mo/yr
|
$33 | - | - | - | - | |
| 06 | 2.7122: Disconnect ballasts | $1,230 | $1,395 |
$618
17,847
kWh
|
$595
-
kW-mo/yr
|
$17 | - | - | - | - | |
| 07 | 2.7261: Install timers and/or thermostats | $1,517 | $1,416 |
$1,497
43,200
kWh
|
- | $20 | - | - | - | - | |
| 08 | 2.7221: Lower temperature during the winter season and vice-versa | $582 | - |
$573
16,572
kWh
|
- | $9 | - | - | - | - | |
| 09 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $557 | $200 |
$209
6,038
kWh
|
$340
-
kW-mo/yr
|
$8 | - | - | - | - | |
| 10 | 3.1193: Convert from batch operation to continuous processing | $6,462 | $6,610 | - | - | - | - |
$5,176
-
lb
|
- | $1,286 | |
| 11 | 4.652: Replace existing equipment with more suitable substitutes | $38,952 | $153,600 | - | - | - | - | - | $38,952 | - | |
| TOTAL RECOMMENDED | $92,238 | $186,079 |
$11,309
326,793
kWh
|
$8,471
-
kW-mo/yr
|
$296 |
$26,748
-
MMBtu
|
$5,176
-
lb
|
$38,952 | $1,286 | ||
| TOTAL IMPLEMENTED | $41,542 | $21,053 |
$6,103
176,392
kWh
|
$8,471
-
kW-mo/yr
|
$220 |
$26,748
-
MMBtu
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs