ITAC Assessment: MS0214
ITAC logo
ITAC Assessment: MS0214
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Industrial lifting equipment
NAICS
n/a
SIC 3537: Industrial Trucks, Tractors, Trailers, and Stackers
Sales Range $50
M
to 100
M
# of Employees 513
Plant Area 474,000
ft2
Annual Production 450
pieces
Production Hrs. Annual 7,000
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $247,968 7,166,700
kWh
Electricity Demand $194,314 18,297
kW-mo/yr
Electricity Fees $6,719 -
Natural Gas $189,608 38,024
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $92,238 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $41,542

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $26,748 $7,400 - - - $26,748
-
MMBtu
- - -
02 2.3191: Use demand controller or load shedder $6,371 $11,500 - $6,276
-
kW-mo/yr
$95 - - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,766 $288 $3,708
107,175
kWh
- $58 - - - -
04 2.7261: Install timers and/or thermostats $3,765 $3,400 $3,709
107,201
kWh
- $56 - - - -
05 2.7144: Install spectral reflectors / delamp $2,288 $270 $995
28,760
kWh
$1,260
-
kW-mo/yr
$33 - - - -
06 2.7122: Disconnect ballasts $1,230 $1,395 $618
17,847
kWh
$595
-
kW-mo/yr
$17 - - - -
07 2.7261: Install timers and/or thermostats $1,517 $1,416 $1,497
43,200
kWh
- $20 - - - -
08 2.7221: Lower temperature during the winter season and vice-versa $582 - $573
16,572
kWh
- $9 - - - -
09 2.1311: Replace electrically-operated equipment with fossil fuel equipment $557 $200 $209
6,038
kWh
$340
-
kW-mo/yr
$8 - - - -
10 3.1193: Convert from batch operation to continuous processing $6,462 $6,610 - - - - $5,176
-
lb
- $1,286
11 4.652: Replace existing equipment with more suitable substitutes $38,952 $153,600 - - - - - $38,952 -
TOTAL RECOMMENDED $92,238 $186,079 $11,309
326,793
kWh
$8,471
-
kW-mo/yr
$296 $26,748
-
MMBtu
$5,176
-
lb
$38,952 $1,286
TOTAL IMPLEMENTED $41,542 $21,053 $6,103
176,392
kWh
$8,471
-
kW-mo/yr
$220 $26,748
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs