Assessment Year | 2002 |
---|---|
Principal Product | Industrial lifting equipment |
NAICS |
n/a
|
SIC | 3537: Industrial Trucks, Tractors, Trailers, and Stackers |
Sales Range | $50 M to 100M |
# of Employees | 513 |
Plant Area |
474,000
ft2
|
Annual Production | 450
pieces
|
Production Hrs. Annual | 7,000
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $247,968 | 7,166,700 |
kWh
|
$0.035 |
Electricity Demand | $194,314 | 18,297 |
kW-mo/yr
|
$10.62 |
Electricity Fees | $6,719 | - |
|
- |
Natural Gas | $189,608 | 38,024 |
MMBtu
|
$4.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $92,238 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $41,542 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $26,748 | $7,400 | - | - | - |
$26,748
-
MMBtu
|
- | - | - | |
02 | 2.3191: Use demand controller or load shedder | $6,371 | $11,500 | - |
$6,276
-
kW-mo/yr
|
$95 | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,766 | $288 |
$3,708
107,175
kWh
|
- | $58 | - | - | - | - | |
04 | 2.7261: Install timers and/or thermostats | $3,765 | $3,400 |
$3,709
107,201
kWh
|
- | $56 | - | - | - | - | |
05 | 2.7144: Install spectral reflectors / delamp | $2,288 | $270 |
$995
28,760
kWh
|
$1,260
-
kW-mo/yr
|
$33 | - | - | - | - | |
06 | 2.7122: Disconnect ballasts | $1,230 | $1,395 |
$618
17,847
kWh
|
$595
-
kW-mo/yr
|
$17 | - | - | - | - | |
07 | 2.7261: Install timers and/or thermostats | $1,517 | $1,416 |
$1,497
43,200
kWh
|
- | $20 | - | - | - | - | |
08 | 2.7221: Lower temperature during the winter season and vice-versa | $582 | - |
$573
16,572
kWh
|
- | $9 | - | - | - | - | |
09 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $557 | $200 |
$209
6,038
kWh
|
$340
-
kW-mo/yr
|
$8 | - | - | - | - | |
10 | 3.1193: Convert from batch operation to continuous processing | $6,462 | $6,610 | - | - | - | - |
$5,176
-
lb
|
- | $1,286 | |
11 | 4.652: Replace existing equipment with more suitable substitutes | $38,952 | $153,600 | - | - | - | - | - | $38,952 | - | |
TOTAL RECOMMENDED | $92,238 | $186,079 |
$11,309
326,793
kWh
|
$8,471
-
kW-mo/yr
|
$296 |
$26,748
-
MMBtu
|
$5,176
-
lb
|
$38,952 | $1,286 | ||
TOTAL IMPLEMENTED | $41,542 | $21,053 |
$6,103
176,392
kWh
|
$8,471
-
kW-mo/yr
|
$220 |
$26,748
-
MMBtu
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs