Assessment Year | 2013 |
---|---|
Principal Product | Treated Water |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | less than $500 k |
# of Employees | 7 |
Plant Area |
467,199
ft2
|
Annual Production | 2,154,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $224,887 | 3,133,871 |
kWh
|
$0.072 |
Electricity Demand | $28,872 | 8,249 |
kW-mo/yr
|
$3.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $62,197 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,312 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $2,448 | $4,896 |
$2,272
32,445
kWh
|
$176
-
kW-mo/yr
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $56,039 | $250,000 |
$52,531
731,631
kWh
|
$3,508
-
kW-mo/yr
|
- | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $846 | $4,207 |
$706
9,828
kWh
|
$567
-
kW-mo/yr
|
$(-427.0)
-
MMBtu
|
|
04 | 2.4133: Use most efficient type of electric motors | $2,864 | $15,486 |
$2,685
37,401
kWh
|
$179
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $62,197 | $274,589 |
$58,194
811,305
kWh
|
$4,430
-
kW-mo/yr
|
$(-427.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,312 | $20,382 |
$4,957
69,846
kWh
|
$355
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs