| Assessment Year | 2002 |
|---|---|
| Principal Product | Upholstered furniture |
| NAICS |
n/a
|
| SIC | 2521: Wood Office Furniture |
| Sales Range | $10 M to 50M |
| # of Employees | 162 |
| Plant Area |
189,671
ft2
|
| Annual Production | 182,500
pieces
|
| Production Hrs. Annual | 2,025
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $36,335 | 908,000 |
kWh
|
$0.040 |
| Electricity Demand | $62,996 | 6,764 |
kW-mo/yr
|
$9.31 |
| Electricity Fees | $5,493 | - |
|
- |
| Natural Gas | $24,860 | 3,685 |
MMBtu
|
$6.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $54,407 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,633 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $2,096 | $1,739 | - | - | - |
$2,096
-
MMBtu
|
- | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,516 | $577 |
$1,494
45,061
kWh
|
- | $22 | - | - | - | - | |
| 03 | 2.2437: Recover waste heat from equipment | $864 | $2,540 | - | - | - |
$864
-
MMBtu
|
- | - | - | |
| 04 | 2.7261: Install timers and/or thermostats | $675 | $472 |
$665
20,063
kWh
|
- | $10 | - | - | - | - | |
| 05 | 2.7122: Disconnect ballasts | $442 | $255 |
$154
4,650
kWh
|
$281
-
kW-mo/yr
|
$7 | - | - | - | - | |
| 06 | 4.132: Purchase new equipment to reduce material use / cost | $48,814 | $175,000 | - | - | - | - |
$9,471
-
lb
|
$5,490 | $33,853 | |
| TOTAL RECOMMENDED | $54,407 | $180,583 |
$2,313
69,774
kWh
|
$281
-
kW-mo/yr
|
$39 |
$2,960
-
MMBtu
|
$9,471
-
lb
|
$5,490 | $33,853 | ||
| TOTAL IMPLEMENTED | $2,633 | $1,304 |
$2,313
69,774
kWh
|
$281
-
kW-mo/yr
|
$39 | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs