Assessment Year | 2002 |
---|---|
Principal Product | Specialized fabricated machinery |
NAICS |
n/a
|
SIC | 3549: Metalworking Machinery, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 87 |
Plant Area |
86,000
ft2
|
Annual Production | 21,600
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $30,625 | 1,941,360 |
kWh
|
$0.016 |
Electricity Demand | $35,978 | 7,094 |
kW-mo/yr
|
$5.07 |
Electricity Fees | $51,243 | - |
|
- |
Natural Gas | $25,544 | 2,313 |
MMBtu
|
$11.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,228 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,665 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $4,200 | $75 | - | - | - | - | - | $4,200 | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,434 | $280 |
$128
13,580
kWh
|
$962
-
kW-mo/yr
|
$344 | - | - | - | |
03 | 2.7261: Install timers and/or thermostats | $822 | $591 |
$230
24,344
kWh
|
- | $592 | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $191 | $158 |
$53
5,659
kWh
|
- | $138 | - | - | - | |
05 | 3.6124: Burn waste oil for heat | $1,741 | $2,012 | - | - | - |
$1,741
-
MMBtu
|
- | - | |
06 | 3.5316: Contract a wood pallet recycling company | $840 | - | - | - | - | - |
$840
-
lb
|
- | |
TOTAL RECOMMENDED | $9,228 | $3,116 |
$411
43,583
kWh
|
$962
-
kW-mo/yr
|
$1,074 |
$1,741
-
MMBtu
|
$840
-
lb
|
$4,200 | ||
TOTAL IMPLEMENTED | $6,665 | $513 |
$181
19,239
kWh
|
$962
-
kW-mo/yr
|
$482 | - |
$840
-
lb
|
$4,200 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs