Assessment Year | 2002 |
---|---|
Principal Product | Drum brakes and disc brakes |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 155 |
Plant Area |
102,000
ft2
|
Annual Production | 1,841,154
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $49,911 | 1,349,941 |
kWh
|
$0.037 |
Electricity Demand | $31,445 | 3,732 |
kW-mo/yr
|
$8.43 |
Electricity Fees | $1,331 | - |
|
- |
Natural Gas | $101,052 | 12,022 |
MMBtu
|
$8.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,733 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2442: Preheat combustion air with waste heat | $22,848 | $50,000 | - | - | - |
$22,848
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,783 | $6,263 |
$3,007
92,907
kWh
|
$2,691
-
kW-mo/yr
|
$85 | - | - | |
03 | 2.4314: Use synthetic lubricant | $1,196 | $264 |
$306
9,379
kWh
|
$271
-
kW-mo/yr
|
$9 | - |
$610
-
gal
|
|
04 | 2.7261: Install timers and/or thermostats | $377 | $236 |
$371
11,430
kWh
|
- | $6 | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $248 | $100 |
$244
7,620
kWh
|
- | $4 | - | - | |
06 | 2.7122: Disconnect ballasts | $146 | $248 |
$76
2,345
kWh
|
$68
-
kW-mo/yr
|
$2 | - | - | |
07 | 2.7261: Install timers and/or thermostats | $135 | $236 |
$133
4,103
kWh
|
- | $2 | - | - | |
TOTAL RECOMMENDED | $30,733 | $57,347 |
$4,137
127,784
kWh
|
$3,030
-
kW-mo/yr
|
$108 |
$22,848
-
MMBtu
|
$610
-
gal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs