Assessment Year | 2001 |
---|---|
Principal Product | Athletic Uniforms |
NAICS |
n/a
|
SIC | 2329: Men's and Boys' Clothing, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 160 |
Plant Area |
35,000
ft2
|
Annual Production | 275,000
pieces
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $43,151 | 657,840 |
kWh
|
$0.066 |
Electricity Demand | $58 | 2,825 |
kW-mo/yr
|
$0.021 |
Electricity Fees | $2,812 | - |
|
- |
Natural Gas | $10,882 | 1,441 |
MMBtu
|
$7.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,384 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,797 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $1,502 | $50 | - | - |
$1,502
-
MMBtu
|
|
02 | 2.7261: Install timers and/or thermostats | $2,283 | $1,063 |
$2,047
39,266
kWh
|
$236 | - | |
03 | 2.2511: Insulate bare equipment | $211 | $24 |
$90
1,723
kWh
|
$10 |
$111
-
MMBtu
|
|
04 | 2.2511: Insulate bare equipment | $162 | $83 |
$69
1,325
kWh
|
$8 |
$85
-
MMBtu
|
|
05 | 2.2136: Install / repair insulation on steam lines | $70 | $88 |
$63
1,202
kWh
|
$7 | - | |
06 | 2.7245: Use direct air supply to exhaust hoods | $2,093 | $1,573 |
$1,876
35,993
kWh
|
$217 | - | |
07 | 2.7124: Make a practice of turning off lights when not needed | $63 | $48 |
$56
1,080
kWh
|
$7 | - | |
TOTAL RECOMMENDED | $6,384 | $2,929 |
$4,201
80,589
kWh
|
$485 |
$1,698
-
MMBtu
|
||
TOTAL IMPLEMENTED | $1,797 | $269 |
$188
3,607
kWh
|
$22 |
$1,587
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs