ITAC Assessment: MS0177
ITAC logo
ITAC Assessment: MS0177
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Military Radar Equipment
NAICS
n/a
SIC 3812: Search, Detection, Navigation, Guidance, Aeronautical, and Nautical Systems and Instruments
Sales Range n/a
# of Employees 600
Plant Area 250,000
ft2
Annual Production 0
units
Production Hrs. Annual 8,736
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $158,713 14,772,000
kWh
Electricity Demand $139,949 29,463
kW-mo/yr
Electricity Fees $364,484 -
Natural Gas $27,688 3,622
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,395 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,329

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $3,133 $630 $545
64,176
kWh
$1,055
-
kW-mo/yr
$1,533
02 2.4221: Install compressor air intakes in coolest locations $196 $209 $34
3,988
kWh
$67
-
kW-mo/yr
$95
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,066 $3,354 $810
95,448
kWh
- $2,256
TOTAL RECOMMENDED $6,395 $4,193 $1,389
163,612
kWh
$1,122
-
kW-mo/yr
$3,884
TOTAL IMPLEMENTED $3,329 $839 $579
68,164
kWh
$1,122
-
kW-mo/yr
$1,628
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs