| Assessment Year | 2001 |
|---|---|
| Principal Product | Military Radar Equipment |
| NAICS |
n/a
|
| SIC | 3812: Search, Detection, Navigation, Guidance, Aeronautical, and Nautical Systems and Instruments |
| Sales Range | n/a |
| # of Employees | 600 |
| Plant Area |
250,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $158,713 | 14,772,000 |
kWh
|
$0.011 |
| Electricity Demand | $139,949 | 29,463 |
kW-mo/yr
|
$4.75 |
| Electricity Fees | $364,484 | - |
|
- |
| Natural Gas | $27,688 | 3,622 |
MMBtu
|
$7.64 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,395 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,329 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $3,133 | $630 |
$545
64,176
kWh
|
$1,055
-
kW-mo/yr
|
$1,533 | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $196 | $209 |
$34
3,988
kWh
|
$67
-
kW-mo/yr
|
$95 | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,066 | $3,354 |
$810
95,448
kWh
|
- | $2,256 | |
| TOTAL RECOMMENDED | $6,395 | $4,193 |
$1,389
163,612
kWh
|
$1,122
-
kW-mo/yr
|
$3,884 | ||
| TOTAL IMPLEMENTED | $3,329 | $839 |
$579
68,164
kWh
|
$1,122
-
kW-mo/yr
|
$1,628 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs