ITAC Assessment: TT0342
ITAC logo
ITAC Assessment: TT0342
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Powdered sugar & Extra Fined granulated sugar
NAICS 311314: Cane Sugar Manufacturing
SIC 2062: Cane Sugar Refining
Sales Range $10
M
to 50
M
# of Employees 10
Plant Area 226,000
ft2
Annual Production 52,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $87,986 1,282,011
kWh
Electricity Demand $64,548 3,445
kW-mo/yr
Electricity Fees $12,750 -
TOTAL YEARLY COSTS $165,284
RECOMMENDED SAVINGS* $68,216 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,622 $450 $5,622
81,958
kWh
- -
02 3.1175: Use a different or recycled raw material $48,835 $16,924 - - $48,835
-
lb
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,629 $950 $1,561
22,745
kWh
$68
-
kW-mo/yr
-
04 2.7135: Install occupancy sensors $867 $1,450 $867
12,636
kWh
- -
05 2.7224: Reduce space conditioning during non-working hours $55 $100 $55
801
kWh
- -
06 2.2437: Recover waste heat from equipment $1,715 $5,000 $1,715
25,000
kWh
- -
07 2.9114: Use solar heat to make electricty $9,493 $73,605 $9,493
138,388
kWh
- -
TOTAL RECOMMENDED $68,216 $98,479 $19,313
281,528
kWh
$68
-
kW-mo/yr
$48,835
-
lb
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs