ITAC Assessment: MS0162
ITAC logo
ITAC Assessment: MS0162
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Catfish Products
NAICS
n/a
SIC 2092: Prepared Fresh or Frozen Fish and Seafoods
Sales Range $10
M
to 50
M
# of Employees 215
Plant Area 45,510
ft2
Annual Production 18,200,000
lb
Production Hrs. Annual 2,080
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $306,004 6,255,569
kWh
Electricity Demand $68,432 17,253
kW-mo/yr
Electricity Fees $(-20,082.0) -
Natural Gas $17,106 3,213
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,316 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,604

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
01 2.2511: Insulate bare equipment $575 $371 - - $575
-
MMBtu
-
02 2.7261: Install timers and/or thermostats $453 $472 $494
11,137
kWh
$(-41.0) - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $429 $158 $468
10,551
kWh
$(-39.0) - -
04 2.2447: Heat water with exhaust heat $4,758 $13,860 - - $4,758
-
MMBtu
-
05 2.7124: Make a practice of turning off lights when not needed $3,175 $2,450 $3,461
76,788
kWh
$(-286.0) - -
06 4.812: Apply for investment incentives $926 $25 - - - $926
TOTAL RECOMMENDED $10,316 $17,336 $4,423
98,476
kWh
$(-366.0) $5,333
-
MMBtu
$926
TOTAL IMPLEMENTED $3,604 $2,608 $3,929
87,339
kWh
$(-325.0) - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs