| Assessment Year | 2000 |
|---|---|
| Principal Product | Catfish Products |
| NAICS |
n/a
|
| SIC | 2092: Prepared Fresh or Frozen Fish and Seafoods |
| Sales Range | $10 M to 50M |
| # of Employees | 215 |
| Plant Area |
45,510
ft2
|
| Annual Production | 18,200,000
lb
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $306,004 | 6,255,569 |
kWh
|
$0.049 |
| Electricity Demand | $68,432 | 17,253 |
kW-mo/yr
|
$3.97 |
| Electricity Fees | $(-20,082.0) | - |
|
- |
| Natural Gas | $17,106 | 3,213 |
MMBtu
|
$5.32 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,316 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,604 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $575 | $371 | - | - |
$575
-
MMBtu
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $453 | $472 |
$494
11,137
kWh
|
$(-41.0) | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $429 | $158 |
$468
10,551
kWh
|
$(-39.0) | - | - | |
| 04 | 2.2447: Heat water with exhaust heat | $4,758 | $13,860 | - | - |
$4,758
-
MMBtu
|
- | |
| 05 | 2.7124: Make a practice of turning off lights when not needed | $3,175 | $2,450 |
$3,461
76,788
kWh
|
$(-286.0) | - | - | |
| 06 | 4.812: Apply for investment incentives | $926 | $25 | - | - | - | $926 | |
| TOTAL RECOMMENDED | $10,316 | $17,336 |
$4,423
98,476
kWh
|
$(-366.0) |
$5,333
-
MMBtu
|
$926 | ||
| TOTAL IMPLEMENTED | $3,604 | $2,608 |
$3,929
87,339
kWh
|
$(-325.0) | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs