ITAC Assessment: MS0151
ITAC logo
ITAC Assessment: MS0151
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Automotive Springs and Idler Arms
NAICS
n/a
SIC 3710:
Sales Range $50
M
to 100
M
# of Employees 240
Plant Area 134,000
ft2
Annual Production 6,800,000
pieces
Production Hrs. Annual 4,500
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $240,429 6,800,410
kWh
Electricity Demand $153,239 17,335
kW-mo/yr
Electricity Fees $6,499 -
Natural Gas $276,888 39,511
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $90,492 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (non-haz) Savings One-time Revenue or Avoided Cost Savings
01 2.3212: Optimize plant power factor $20,769 $17,100 - - $20,769 - - -
02 2.8114: Change rate schedules or other changes in utility service $4,446 $100 - $4,446
-
kW-mo/yr
- - - -
03 2.7447: Install vinyl strip / high speed / air curtain doors $6,122 $4,900 $6,032
171,747
kWh
- $90 - - -
04 3.3131: Use evaporation to concentrate material $42,063 $39,781 - - - $63
-
MMBtu
$42,000
-
gal
-
05 4.821: Pay bills on time to avoid late fees $17,092 $100 - - - - - $17,092
TOTAL RECOMMENDED $90,492 $61,981 $6,032
171,747
kWh
$4,446
-
kW-mo/yr
$20,859 $63
-
MMBtu
$42,000
-
gal
$17,092
TOTAL IMPLEMENTED - - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs