Assessment Year | 1999 |
---|---|
Principal Product | Clay Construction Brick |
NAICS |
n/a
|
SIC | 3251: Brick and Structural Clay Tile |
Sales Range | $1 M to 5M |
# of Employees | 38 |
Plant Area |
56,685
ft2
|
Annual Production | 25,000,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $105,355 | 2,950,762 |
kWh
|
$0.036 |
Electricity Demand | $89,975 | 9,517 |
kW-mo/yr
|
$9.45 |
Electricity Fees | $3,223 | - |
|
- |
Natural Gas | $322,670 | 106,840 |
MMBtu
|
$3.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,021 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,294 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $790 | $263 |
$778
23,154
kWh
|
$12 | - | |
02 | 2.7261: Install timers and/or thermostats | $74 | $119 |
$73
2,052
kWh
|
$1 | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,504 | $2,060 | - | - |
$1,504
-
MMBtu
|
|
04 | 2.2515: Use optimum thickness insulation | $15,653 | $9,593 | - | - |
$15,653
-
MMBtu
|
|
TOTAL RECOMMENDED | $18,021 | $12,035 |
$851
25,206
kWh
|
$13 |
$17,157
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,294 | $2,323 |
$778
23,154
kWh
|
$12 |
$1,504
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs