Assessment Year | 1998 |
---|---|
Principal Product | Cans/Ends |
NAICS |
n/a
|
SIC | 3829: Measuring and Controlling Devices, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 300 |
Plant Area |
394,113
ft2
|
Annual Production | 300,000,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $433,461 | 7,937,866 |
kWh
|
$0.055 |
Electricity Demand | $193,897 | 15,221 |
kW-mo/yr
|
$12.74 |
Natural Gas | $421,834 | 106,301 |
MMBtu
|
$3.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $574,642 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,726 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,737 | - |
$1,737
6,155
kWh
|
- | - | - | - | |
02 | 2.2511: Insulate bare equipment | $555 | $349 |
$555
10,258
kWh
|
- | - | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $3,271 | $2,284 |
$2,381
42,497
kWh
|
$890
-
kW-mo/yr
|
- | - | - | |
04 | 2.7134: Use photocell controls | $1,199 | $1,000 |
$575
10,551
kWh
|
$624
-
kW-mo/yr
|
- | - | - | |
05 | 2.7135: Install occupancy sensors | $1,711 | $2,464 |
$1,145
21,102
kWh
|
$566
-
kW-mo/yr
|
- | - | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $1,122 | $1,600 |
$920
16,999
kWh
|
$202
-
kW-mo/yr
|
- | - | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,821 | $7,370 |
$3,521
64,478
kWh
|
$1,300
-
kW-mo/yr
|
- | - | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $2,993 | $4,500 |
$2,181
39,859
kWh
|
$812
-
kW-mo/yr
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,253 | $17,610 |
$7,198
131,887
kWh
|
$3,055
-
kW-mo/yr
|
- | - | - | |
10 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $76,331 | $262,000 |
$116,032
2,125,147
kWh
|
$43,388
-
kW-mo/yr
|
$(-83,089.0)
-
MMBtu
|
- | - | |
11 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $3,974 | - | - | - | - |
$3,974
-
lb
|
- | |
12 | 3.5313: Increase amount of waste recovered for resale | $3,575 | - | - | - | - |
$3,575
-
lb
|
- | |
13 | 3.1162: Use less wasteful packaging | $48,140 | $30,000 | - | - | - |
$48,140
-
lb
|
- | |
14 | 4.441: Install automatic packing equipment | $207,480 | $100,700 | - | - | - | - | $207,480 | |
15 | 4.445: Install equipment to move product | $207,480 | $100,000 | - | - | - | - | $207,480 | |
TOTAL RECOMMENDED | $574,642 | $529,877 |
$136,245
2,468,933
kWh
|
$50,837
-
kW-mo/yr
|
$(-83,089.0)
-
MMBtu
|
$55,689
-
lb
|
$414,960 | ||
TOTAL IMPLEMENTED | $18,726 | $23,707 |
$13,591
222,450
kWh
|
$5,135
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs