ITAC Assessment: MS0144
ITAC logo
ITAC Assessment: MS0144
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product softwood lumber
NAICS
n/a
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area
n/a
Annual Production 43,000
thousand feet
Production Hrs. Annual 8,760
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $111,910 3,314,771
kWh
Electricity Demand $115,485 12,328
kW-mo/yr
Electricity Fees $5,536 -
Natural Gas $261,888 83,450
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,345 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (non-haz) Savings
01 2.7261: Install timers and/or thermostats $334 $236 $329
9,672
kWh
- $5 - -
02 2.8114: Change rate schedules or other changes in utility service $20,924 - - $24,303
-
kW-mo/yr
$(-3,379.0) - -
03 3.6124: Burn waste oil for heat $638 $2,461 - - - - $638
-
gal
04 2.8112: Combine utility meters $449 $1,052 - - - $449
-
MMBtu
-
TOTAL RECOMMENDED $22,345 $3,749 $329
9,672
kWh
$24,303
-
kW-mo/yr
$(-3,374.0) $449
-
MMBtu
$638
-
gal
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs