| Assessment Year | 1999 |
|---|---|
| Principal Product | Wood Household Furniture |
| NAICS |
n/a
|
| SIC | 2511: Wood Household Furniture, Except Upholstered |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
235,000
ft2
|
| Annual Production | 200,000
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $99,677 | 3,011,430 |
kWh
|
$0.033 |
| Electricity Demand | $121,273 | 12,933 |
kW-mo/yr
|
$9.38 |
| Electricity Fees | $(-1,314.0) | - |
|
- |
| Natural Gas | $6,554 | 1,117 |
MMBtu
|
$5.87 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,490 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4314: Use synthetic lubricant | $2,471 | $825 |
$591
17,878
kWh
|
$1,136
-
kW-mo/yr
|
$(-81.0) | - | $825 | |
| 02 | 2.3132: Recharge batteries on during off-peak demand periods | $405 | - | - |
$424
-
kW-mo/yr
|
$(-19.0) | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,411 | $1,101 |
$1,486
44,842
kWh
|
- | $(-75.0) | - | - | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $5,726 | $12,791 |
$4,525
136,577
kWh
|
$5,093
-
kW-mo/yr
|
$(-460.0) |
$(-3,432.0)
-
MMBtu
|
- | |
| 05 | 2.7261: Install timers and/or thermostats | $477 | $708 |
$502
15,240
kWh
|
- | $(-25.0) | - | - | |
| TOTAL RECOMMENDED | $10,490 | $15,425 |
$7,104
214,537
kWh
|
$6,653
-
kW-mo/yr
|
$(-660.0) |
$(-3,432.0)
-
MMBtu
|
$825 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs