ITAC Assessment: MS0138
ITAC logo
ITAC Assessment: MS0138
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Dust Collection Systems and Replacement Parts
NAICS
n/a
SIC 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment
Sales Range $10
M
to 50
M
# of Employees 84
Plant Area 68,380
ft2
Annual Production 200,240
pieces
Production Hrs. Annual 3,120
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,528 663,540
kWh
Electricity Demand $23,705 3,257
kW-mo/yr
Electricity Fees $1,200 -
Natural Gas $10,815 2,237
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,972 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,197

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings
01 2.4221: Install compressor air intakes in coolest locations $187 $197 $80
2,345
kWh
$104
-
kW-mo/yr
$3 - - -
02 2.6214: Shut off pilots in standby equipment $884 $80 - - - $884
-
MMBtu
- -
03 2.2437: Recover waste heat from equipment $1,777 $1,994 - - - $1,777
-
MMBtu
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,462 $266 $2,426
74,736
kWh
- $36 - - -
05 2.7111: Reduce illumination to minimum necessary levels $3,832 $3,788 $1,592
48,945
kWh
$2,183
-
kW-mo/yr
$57 - - -
06 2.4314: Use synthetic lubricant $4,376 $825 $709
21,102
kWh
$820
-
kW-mo/yr
- - $1,180
-
gal
$1,667
07 3.6124: Burn waste oil for heat $1,399 $2,555 - - - $141
-
MMBtu
$1,258
-
gal
-
08 3.2123: Convert to high volume low pressure (hvlp) paint guns $18,055 $720 - - - - $18,055
-
gal
-
TOTAL RECOMMENDED $32,972 $10,425 $4,807
147,128
kWh
$3,107
-
kW-mo/yr
$96 $2,802
-
MMBtu
$20,493
-
gal
$1,667
TOTAL IMPLEMENTED $27,197 $7,045 $4,098
126,026
kWh
$2,287
-
kW-mo/yr
$96 $2,661
-
MMBtu
$18,055
-
gal
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs