| Assessment Year | 1998 |
|---|---|
| Principal Product | Prepared Poultry |
| NAICS |
n/a
|
| SIC | 2015: Poultry Slaughtering and Processing |
| Sales Range | $10 M to 50M |
| # of Employees | 160 |
| Plant Area |
37,800
ft2
|
| Annual Production | 20,800,000
lb
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $130,680 | 2,938,746 |
kWh
|
$0.044 |
| Electricity Demand | $28,623 | 6,365 |
kW-mo/yr
|
$4.50 |
| Electricity Fees | $(-14,507.0) | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $15,999 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,233 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,761 | $6,971 |
$2,697
85,580
kWh
|
$531
-
kW-mo/yr
|
$(-467.0) | - | - | - | - | |
| 02 | 2.2437: Recover waste heat from equipment | $2,888 | $3,952 | - | - | - |
$2,888
-
MMBtu
|
- | - | - | |
| 03 | 2.7261: Install timers and/or thermostats | $125 | $236 |
$151
4,689
kWh
|
- | $(-26.0) | - | - | - | - | |
| 04 | 3.1161: Eliminate/reduce an operation | $3,255 | - | - | - | - | - | - | $477 | $2,778 | |
| 05 | 3.4151: Minimize water usage | $279 | $10 | - | - | - | - |
$279
-
Tgal
|
- | - | |
| 06 | 4.652: Replace existing equipment with more suitable substitutes | $5,878 | $14,990 |
$1,246
47,773
kWh
|
$342
-
kW-mo/yr
|
- | - | - | $1,080 | $3,210 | |
| 07 | 4.821: Pay bills on time to avoid late fees | $813 | $324 | - | - | $813 | - | - | - | - | |
| TOTAL RECOMMENDED | $15,999 | $26,483 |
$4,094
138,042
kWh
|
$873
-
kW-mo/yr
|
$320 |
$2,888
-
MMBtu
|
$279
-
Tgal
|
$1,557 | $5,988 | ||
| TOTAL IMPLEMENTED | $7,233 | $7,541 |
$2,848
90,269
kWh
|
$531
-
kW-mo/yr
|
$320 | - |
$279
-
Tgal
|
$477 | $2,778 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs